Durable Link Slab for Jointless Bridge Decks
Based on Strain-Hardening Cementitious Composites
Construction Timeline

In cooperation with the Michigan Department of Transportation (MDOT), HNTB Engineering Consultants, Midwest Bridge Contractors, and Clawson Concrete Company, construction of a demonstration ECC link slab began in July, 2005. The southeastern Michigan project site is Grove Street over Interstate 94 (S02 of 81063) in Ypsilanti, approximatly 45 minutes outside of Detroit, Michigan. The bridge is being reconstructed in two halves, with Phase 1 nearing completion in late September. Through the cooperation of state transportation officials, industry consulting engineers and contractors, and ACE-MRL research personnel, this first infrastructure demonstration project of ECC material in the US is scheduled for completion in mid-November. Please follow along as the project nears completion. This site will be updated periodically with further developments and pictures as construction progresses.

More to follow! Please visit often!

Date
Activity
Photos

September10
Phase 1
Pouring of ECC link slab.

Prepared Link Slab

Placement of ECC

Placement of ECC

Screeding of Link Slab

Arrival of Concrete Trucks

Placement of ECC

Self-Consolidating ECC

Finished Link Slab


August 25 - September 6
Phase 1

Completed stay-in-place formwork, installation of concrete deck reinforcing steel bars, and preparation of link slab formwork.

Completed Formwork

Installation of Rebar

Completion of Rebar

Installation of Rebar

Link Slab Preparation

Link Slab Preparation


August 4 - August 25
Phase 1

Cleaning of steel girders, removal of old shear connectors, installation of stay-in-place formwork, and installation of new shear connectors.

Cleaned Girders

Girder Preparation

New Shear Connectors

Link Slab Location

Stay-in-Place Formwork

Sandblasting Girders


August 2
Phase 1

Completion of concrete deck demolition and preparation of exisiting steel girders.

Completion of Demolition

Removal of Shear Studs

Completion of Demolition

Steel Girders


July 28 - August 1
Phase 1

Night demolition of concrete bridge deck.

Night Demolition

Night Demolition


July 26
Phase 1

Removal of temporary bituminous asphalt riding surface on bridge deck.

Removal of Asphalt Surface

Removal of Asphalt Surface


July 23

ECC trial mixing at Clawson Concrete.

Concrete Truck Mixing

Discharging ECC from Truck

Self-Consolidating ECC

Screeding of ECC


July 5

Grove Street bridge before any construction activity.

Grove Street Before

Grove Street Over I-94

Joints Before Link Slab

Bridge Pier Under Link Slab